The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

A、 Contingency reserve B、 Project profit C、 Management reserve D、 Special fund

时间:2024-06-04 14:39:01

相似题目